The owner remained firm with the December date, for opening of the Gaming area, whose scope now included two additional bars and restaurant. However the project did not become fully funded until late July, removing 8 weeks from the initial schedule. The project was initially projected to start late spring 2012, with the opening of the Gaming Floor by Christmas. Architectural and Engineering firms were hired by the Casino to provide the full design of the 16,000 square foot wing of the facility, including its mechanical and electrical systems. Replacement of the aging HVAC system with a new system capable of ventilating the space using 100% outside air with heat recovery.